What To Expect / The Process

A primary goal of NJ Modular Solutions is to make the modular home process as easy as possible. We will work with you from start to finish to make sure your project stays on-time and on-budget. Our modular home building process has been developed with more than 40 years of experience to ensure that your home is constructed efficiently and correctly. Our turn key process means that you can be in your new home in as little as 120 working days from the house being set.

The following is an overview of the typical turn-key modular home process. Actual process may vary.

Land/Lot Development

  1. Purchase
  2. Clear title (if not already owned)
  3. Accessible to modular transporter (conduct site accessibility study, conduct prior to purchase if not already owned)
  4. Perk/probe test or public sewer if available (conduct prior to purchase if not already owned)
  5. Land surveyed (if not already owned)

Forms/Procedures/Permits

  1. Select modular model, options
  2. Develop and finalize prints, plans, options, finishes and specs
  3. Contracts signed
  4. Sign-off on plans and specs
  5. Secure financing*
  6. Set target occupancy date
  7. Issue deposit
  8. Establish construction activities/schedule
  9. Obtain and post permits (building, electrical, plumbing, mechanical, road/culvert)
  10. Application for gas/electrical service
  11. Site survey (stake out)

Foundation and Site Work

  1. Order steel beams and columns
  2. Deliver dumpster and port-a-potty
  3. Site preparation, remove obstacles
  4. Layout and excavation
  5. Form footings
  6. Pour footings
  7. Footing inspection
  8. Install footing drains and basement stone
  9. Install under-slab utilities
  10. Block delivery/foundation systems
  11. Construct/install foundation walls
  12. Inspect foundation drains
  13. Apply foundation damp-proofing and vapor barrier
  14. Install anchor clips/bolts, sill plate and sealer
  15. Install sump pump crock and rough plumbing
  16. Install basement windows
  17. Install foundation drain tile and cover
  18. Prep opening in floor for posts/support columns
  19. Pour basement floor
  20. Backfill

Site Preparation

  1. Foundations and footings are completed
  2. Foundation is square and level
  3. Foundation and footings have passed inspection
  4. Obstacles for crane and transporters have been removed
  5. Access route for crane and transporters is planned
  6. Crane pad is ready and firm
  7. Set crew and crane schedules are confirmed
  8. Bulldozer and operator scheduled and confirmed
  9. Utility crews have been scheduled for turn-off/turn-on (if applicable)
  10. Weather forecast for set day looks adequate

Payment for delivery day confirmed and available


Modular Home Set

  1. Modules delivered/received
  2. Unwrap modules
  3. Check inventory of ship-loose materials
  4. Mark mating lines on the foundation
  5. Locate pick-points on the modules, prepare for lifting
  6. Module set
  7. Fasten and check module
  8. Prepare mating surfaces
  9. Prepare wires, pipes, ducts and stairs
  10. Posts/support columns set/installed
  11. Lift jointed roof sections with crane
  12. Lift dormers and other roof elements
  13. Make the home weather-tight and secure
  14. Sign set-release

Exterior Finishing

  1. Siding completed
  2. Masonry work completed
  3. Prime, paint or stain exterior surfaces
  4. Install shutters
  5. Install chimney stack
  6. Install gutters and downspouts
  7. Optional garages completed
  8. Optional porches, decks and patios completed

Interior Electrical

  1. Install circuit breaker box
  2. Install meter box, conduit master, service entrance cable & basement cable
  3. Connect wiring of modular units and tie-in to junction box
  4. Connect service in garage and outbuildings if applicable
  5. Install sump pump
  6. Install 220v service for range/dryer
  7. Electrical inspection

Plumbing Connections

  1. Drill/install well & pump or hook-up to public system
  2. Install/inspect septic and drainage systems of hook-up to public systems
  3. Install shower doors
  4. Install supply and drain lines/connect to stubbing
  5. Install gas pipes to range/dryer/water heater if applicable
  6. Check and tighten shut-off valves
  7. Plumbing inspection

HVAC

  1. Install/connect ac system
  2. Install oil tank and line to furnace if applicable
  3. Install electric water heater and connect to breaker box
  4. Connect chimney flue into furnace
  5. For baseboard electrical heat, connect circuits at junction box
  6. Vent dryer
  7. Mechanical inspection

Interior Finishing

  1. Finish/patch drywall
  2. Paint interior walls
  3. Finish interior trim and doors/adjust
  4. Install or seam vinyl, hardwood, laminate or carpeting at mate walls
  5. Stairs to basement set/installed
  6. Clean-up

Exterior Final Finish

  1. Complete garage floors, steps, service walks, etc.
  2. Install exterior lights and bulbs
  3. Finish grading
  4. Landscaping
  5. Garage doors
  6. Exterior clean-up

Closing

  1. Punch list
  2. Final clean-up – remove dumpsters & port-a-potty
  3. Walk through with customer
  4. Final building inspection
  5. Occupancy permit
  6. Owner occupancy